Schedule and Traffic Impacts
Page last updated: Aug. 7, 2026
Schedule: April 20 to Oct. 30, 2026
Anticipated work scheduled: Crews will:
- Finish asphalt surface removal along northbound US 45 and sideroads
- Grade for new guardrail installation
- Grade and place base material for paving
- Repair the bridge deck
- Install storm sewer
Traffic impacts (the next 10 days):
- Traffic is shifted to southbound US 45, with one lane per direction until October
- Motorists will encounter flaggers near the intersections. Traffic may be directed to use the nearest connected intersection during paving operations.