US 45, County C to Gollnow Road

 Waupaca and Shawano Counties

Schedule and Traffic Impacts

Page last updated: Aug. 7, 2026

Schedule: April 20 to Oct. 30, 2026

Anticipated work scheduled: Crews will:

  • Finish asphalt surface removal along northbound US 45 and sideroads
  • Grade for new guardrail installation
  • Grade and place base material for paving
  • Repair the bridge deck
  • Install storm sewer

Traffic impacts (the next 10 days): 

  • Traffic is shifted to southbound US 45, with one lane per direction until October
  • Motorists will encounter flaggers near the intersections. Traffic may be directed to use the nearest connected intersection during paving operations.