Schedule
Construction begins: April 20, 2026
Anticipated completion: early August 2026
Traffic impacts
US 18 and WIS 23 intersections will have lane closures
Weekly update
Current Construction Operations (Week of 7/27/2026):
- Concrete sidewalk completed
- Permanent pavement markings completed
- Permanent signing completed
- Topsoil/restoration completed
- Project wide sweeping completed
- Removal of all traffic and erosion control items completed
- Project completion on 7/30/26
- No work anticipated over weekend (8/1/26 – 8/2/26)
Upcoming Construction Operations (Week of 8/3/2026):
- Minor miscellaneous project punch list items
Current Traffic Information:
- The project is now in its post stage and traffic is now in its permeant traffic pattern post construction. Currently traffic is being delineated using traffic control drums until the permeant pavement markings can be installed. See the attached plan sheets for the permeant pavement markings layout and traffic pattern.
- Post stage maps