Schedule
Construction begins: April 20, 2026
Anticipated completion: early August 2026
Traffic impacts
US 18 and WIS 23 intersections will have lane closures
Weekly update
Current Construction Operations (Week of 7/6/2026):
- Pouring of concrete pavement along WIS 23 and Johns St completed
- Pouring of concrete median along WIS 23 completed
- Asphalt paving on Johns St
- Permanent Pavement markings on US 18, County YZ/King St, and WIS 23 north of County YZ intersection completed
- Traffic signal installation to continue at both intersections
- No work anticipated over weekend (7/11/26 – 7/12/26)
Upcoming Construction Operations (Week of 7/13/2026):
- Permanent signing installation
- Permanent pavement markings on remainder of project
- Topsoil/restoration project wide
- No work anticipated over weekend (7/18/26 – 7/19/26)
Current Traffic Information:
- There are various lane closures for stage 5 (US 18/WIS 23) & 2 (US 18/Johns St). These closures will be continuous and last until the completion of each stage.
Lane Closures
US 18/WIS 23 Intersection
- WIS 23 NB – left lane and left turn lane closed
- WIS 23 SB – left lane and left turn lane closed
US 18/Johns St Intersection
- Johns St NB – left turn lane closed
- Johns St SB – left turn lane closed