Schedule
Construction begins: April 20, 2026
Anticipated completion: early August 2026
Traffic impacts
US 18 and WIS 23 intersections will have lane closures
Weekly update
Current Construction Operations (Week of 5/4/2026):
- Pavement sawing within the east and west medians of US 18 at both intersections, at the north and south medians of Johns St, and the NE/SE sidewalk quadrants of Johns St was completed
- Pavement and curb & gutter removal within the medians/left turn lanes of US 18 at both intersections
- Base aggregate placement within the medians/left turn lanes of US 18 at both intersections
- Storm sewer removal/install within the medians of US 18 at both intersections
- No work anticipated over weekend (5/9/26 – 5/10/26)
Upcoming Construction Operations (Week of 5/11/2026):
- Pavement/Curb & gutter removal, base aggregate placement, and storm sewer removal/install to continue
- Concrete pavement and curb & gutter to be poured towards the end of the week
- No work anticipated over weekend (5/16/26 – 5/17/26)
Current Traffic Information:
- The inside lane and left turn lanes of US 18 will continue to be closed to traffic to allow for stage 1 construction operations. This closure will be continuous and last until the completion of stage 1 which is tentatively scheduled through 5/22/26.
- Stage 1 closure
Lane Closures
US 18/WIS 23 Intersection
- US 18 EB – inside lane and left turn lane
- US 18 WB – inside lane and left turn lane
US 18/Johns St Intersection
- US 18 EB – inside lane and left turn lane
- US 18 WB – inside lane and left turn lane