Schedule
Check out the weekly update
Pre-construction public meeting: March 11, 2025
Construction starts: March 17, 2025
THE FOLLOWING WORK WAS COMPLETED in 2025:
- Bridge Widenings – County G, US 18/151 over the Sugar River, eastbound on-ramp from
W. Verona Ave - County G/Dairy Ridge Road Interchange – ramp and roadway improvements, new traffic signal
3. Auxiliary lanes added – both eastbound and westbound between County G and W. Verona Ave; eastbound between W. Verona Ave and WIS 69 - W. Verona Ave Interchange – 2nd lane added to the eastbound on-ramp
- Military Ridge Trail box culvert extensions – both sides of US 18/151 to accommodate new auxiliary lanes
Anticipated completed: June 2026
- Final items in the Spring include permanent grooved pavement markings on US 18/151 from County G to WIS 69 and bridge improvement work on the median sides of both Sugar River Bridges
Traffic impacts
US 18/151 will remain open to traffic under lane closures and ramp closures.