US 18/151 (County G to WIS 69)

Verona, Dane County

Schedule

Check out the weekly update

Pre-construction public meeting: March 11, 2025

Construction starts: March 17, 2025

THE FOLLOWING WORK WAS COMPLETED in 2025:

  1. Bridge Widenings – County G, US 18/151 over the Sugar River, eastbound on-ramp from
    W. Verona Ave
  2. County G/Dairy Ridge Road Interchange – ramp and roadway improvements, new traffic signal
    3. Auxiliary lanes added – both eastbound and westbound between County G and W. Verona Ave; eastbound between W. Verona Ave and WIS 69
  3. W. Verona Ave Interchange – 2nd lane added to the eastbound on-ramp
  4. Military Ridge Trail box culvert extensions – both sides of US 18/151 to accommodate new auxiliary lanes

Anticipated completed: June 2026

  • Final items in the Spring include permanent grooved pavement markings on US 18/151 from County G to WIS 69 and bridge improvement work on the median sides of both Sugar River Bridges

 

Traffic impacts

US 18/151 will remain open to traffic under lane closures and ramp closures.