Schedule
Check out the weekly update
Construction starts: March 17, 2025
Anticipated completed: June 2026
- Final items in the spring include permanent grooved pavement markings on US 18/151 from County G to WIS 69 and bridge improvement work on the median sides of both Sugar River bridges
- 2026 update
Traffic impacts
US 18/151 will remain open to traffic under lane closures and ramp closures.