Schedule
Construction begins: May 26, 2026
Anticipated completion: 2026
Traffic impacts
The road will remain open with shoulder and/or lane closures during construction
Project update
Work in the first stage consists of constructing the new outside right-turn lanes on each side of County F and should last until late June
- Removals
- Grading for the right turn lane to County F
- Storm sewer along the south side of US 18
- Landscaping/restoration
- Base aggregate
- Concrete curb and gutter
- HMA pavement
Traffic for Stage 1:
- Eastbound right lane will be closed from approximately the County line to County F.
- Westbound right lane will be closed from approximately Cave of the Mounds Rd to County F.
- County F will remain open
- Please drive with caution through the construction zone. Speed limit will be reduced to 55mph during construction activity