Schedule
Construction begins: May 26, 2026
Anticipated completion: early September 2026
Traffic impacts
The road will remain open with shoulder and/or lane closures during construction
Project update
Construction of the new RCUT intersection of US 18/151 at County F continues. During the Stage 1 work, the contractor has performed grading for both the eastbound and westbound new right turn lanes to County F. Storm sewer work has also been completed.
Work to complete Stage 1 over the next two weeks includes:
- Concrete curb and gutter
- HMA pavement for the new right turn lanes onto County F
- Landscaping, restoration
- Signing
It is anticipated to switch into Stage 2A work before July 3rd, weather permitting. Stage 2A will be work in the median of US 18/151, and US 18/151 traffic moved to the outside lane. County F will be open for Stage 2A.