Schedule
Stage 1 March 23 – April 2026 (Inside lane work)
Stage 2 April 2026 – Mid July (Move all traffic to EB lanes and replace pavement in WB lanes)
Stage 3 Mid July 2026 – mid-September 2026 (Move all traffic to WB lanes and replace pavement in EB lanes)
- Weather Dependent all of Stage 2 work is planned to be completed by June 29 or 30th and traffic will begin to be shifted into the same one lane bi-directional configuration onto the newly installed West Bound lanes. Work in Stage 3 is scheduled to last until mid-September 2026. Work in Stage 3 will include concrete pavement removal, excavation, new rock subbase, new concrete pavement and upgraded signalized intersections.
Stage 4 September 2026 – November 2026 (finish inside lane and signals)
Traffic impacts
US 14 will be open to through traffic and access to residents and businesses will be maintained at all times.