Schedule
Stage 1 March – April 2026 (Inside lane work)
Stage 2 April 2026 – Mid July (Move all traffic to EB lanes and replace pavement in WB lanes)
Stage 3 Mid July 2026 – October 2026 (Move all traffic to WB lanes and replace pavement in EB lanes)
Stage 4 October 2026 – November 2026 (finish inside lane and signals)
Traffic impacts
US 14 will be open to through traffic and access to residents and businesses will be maintained at all times.