South section – Schedule
For more information on Public Involvement Meetings (PIM), hearings and other public activities, visit Public involvement.
Current (this year)
2016
- Construction continues on US 12 bypass from Terrytown Road to Point of Rocks
- Construction continues on large bridges at Baraboo River, Skillet Creek and Skillet Creek Tributary
- County Highway W roadway work scheduled to be complete
- Fall – US 12 construction begins south of Point of Rocks to Lehman Road
Future (next year and beyond)
- Fall 2017 or later – Construction scheduled to be completed
Past (anything prior to today)
2011-2014 – Continue right of way acquisition and complete final roadway plans
2010
- Winter 2010 – Started appraisals and negotiations for purchase of right of way
- Summer 2010 – Finalize preliminary roadway plans, update environmental study, and prepare final right of way plat
- Jan. 13, 2010 – PIM
2007 – Design work started