US 10 Westbound, Old WIS 49 to Winnebago County Line

Waupaca County

Schedule and Traffic Impacts

Page last updated: Sept. 4, 2026

Schedule: Aug. 10 to Nov. 12, 2026

Anticipated work scheduled: Crews will:

  • Grade at guardrail locations
  • Complete concrete pavement saw cutting
  • Start concrete pavement repair and replacement

Traffic impacts (the next 10 days): 

  • The westbound inside lane (passing lane) and shoulder of US 10 will be closed from Marsh Road to Old WIS 49.
  • The inside shoulder of eastbound US 10 will have temporary closures to complete work at maintenance crossovers.