US 10, Anderson Road to Appletree Lane

 Waupaca County

Schedule and Traffic Impacts

Page last updated: July 24, 2026

Schedule: May 4 to Aug. 17, 2026

Anticipated work scheduled: Crews will:

  • US 10 westbound
    • Continue saw cutting concrete pavement for concrete pavement repair and replacement
    • Continue concrete pavement repair and replacement on the outside lane (driving lane)
  • US 10 eastbound
    • Pour concrete for the parapet repair at the bridge over WIS 54
  • WIS 49/54
    • Complete concrete pavement repair and replacement on ramps and WIS 49/54
    • Pave asphalt shoulder
  • Churchill
    • Pave asphalt shoulder
    • Complete concrete pavement repair and replacement

Traffic impacts (the next 10 days): 

  • US 10
    • The westbound outside lane (driving lane) and shoulder are closed from Vaughan Road to Anderson Road.
    • The Eastbound inside lane (passing lane) and shoulder are closed from Anderson Road to WIS 54.
  • WIS 22 South / Lakeside Parkway
    • The southbound inside lane is closed from 1/4 mile north to 1/4 mile south of US 10.
    • The northbound outside lane is closed from 1/4 mile north to 1/4 mile south of US 10.
  • WIS 49/54
    • The eastbound off ramp from US 10 will be closed. Motorist should follow posted detour.
    • The westbound on ramp to US 10 will be closed. Motorist should follow posted detour.
    • The eastbound and westbound outside lane and shoulder will be closed from west of County QQ to Covered Bridge Road. Motorists can anticipate delays.
  • Churchill
    • All eastbound and westbound ramps to and from US 10 will be closed. There will be no posted detour.