US 10, Anderson Road to Appletree Lane

 Waupaca County

Schedule and Traffic Impacts

Page last updated: April 30, 2026

Schedule: May 4 to July 31, 2026

Anticipated work scheduled: Crews will:

  • US 10 westbound
    • Install traffic control
    • Install erosion control
    • Install turtle exclusion fencing
    • Remove existing asphalt shoulder
  • WIS 22 South/Lakeside Parkway
    • Install traffic control
    • Saw existing concrete pavement

Traffic impacts (the next 10 days): 

  • US 10
    • Starting May 4, 2026, the westbound outside lane (driving lane) and shoulder will be closed from Vaughan Road to Anderson Road.
  • WIS 22 South / Lakeside Parkway
    • Starting May 4, 2026, the southbound outside lane (driving lane) will be closed from ¼ mile north to ¼ mile south of US 10.
    • Starting May 4, 2026, the northbound inside lane (passing lane) will be closed from ¼ mile north to ¼ mile south of US 10.