Traffic Impacts
The following traffic impacts are planned for the following segments:
- Southbound WIS 124: Duncan Creek Bridge to North Bridge Street:
- During construction:
- Southbound WIS 124 will be closed starting at West Spring Street.
- The West River Street/Bay Street intersection is closed.
- Detour: West River Street Westbound Traffic
- Detour: West River Street Eastbound and WIS 124 Southbound Traffic
- The intersection closure is expected to be open by April 30.
- During construction:
- North- and Southbound WIS 124: Duncan Creek to County S:
- During construction:
- Northbound WIS 124 will be closed at the County S roundabout for about three weeks.
- Motorists will encounter lane shifts and shoulder closures for remaining work.
- During construction: