Project Overview
Construction includes:
- Removing the pavement from east of the Buffalo River State Park Trail to just west of Rose Lane and replacing it with 8.5 inches of concrete pavement along with 6 inches of underlying base aggregate
- Repairing or replacing existing concrete pavement near I-94 at spot locations
- Making concrete surface repairs on the bridge over the north fork of the Buffalo River and overlaying the deck with new pavement
- Replacing storm sewer, sanitary sewer and water main
- Replacing sidewalk, curb ramps, curb and gutter
- Replacing pavement markings