I-94, Kinney Road and 100th Street Bridges

 St. Croix County

Project Overview

Construction in 2024 includes:

  • Removing trees to the north of westbound I-94.
  • Building temporary crossovers on both sides of each bridge.
  • Building temporary bridges in the median at Kinney Road and 100th Street, along with temporary lanes of I-94.
  • Installing permanent storm sewer pipes at Kinney Road.

Construction in 2025 includes:

  • Building new westbound bridges at Kinney Road and 100th Street.
  • Replacing 1,000 to 1,200 feet pavement on westbound I-94 on both sides of the structures.

Construction in 2026 includes:

  • Building new eastbound bridges at Kinney Road and 100th Street
  • Replacing 1,000 to 1,200 feet pavement on eastbound I-94 on both sides of the structures.
  • Removing temporary structures and lanes.