I-94 Hudson, WIS 35–US 12

Hudson

Schedule

Project start date: March 28, 2018
Project completion: November 21, 2018

Traffic Impacts

  • A section of IH-94 WB and EB from the Wisconsin/Minnesota border to STH 35S will have nighttime single lane closures.
  • STH 35N SB to IH-94 EB on-ramp, 14TH Street on-ramp, and I-94 WB off-ramp to STH 35N will be closed until mid-October. Detours will be posted.
  • I-94 WB from Mile Maker 5 to WI/MN border, and on I-94 EB from WI/MN border to STH 35S the speed will be reduced from 70 MPH to 60 MPH. STH 35S speed will be reduced from 65 MPH to 55 MPH