Schedule and Traffic Impacts
Page last updated: July 24, 2026
Schedule: April 22 to September 2026
Anticipated work scheduled for next week: Crews will:
- Finish paving asphalt in the outside driving lane and begin shouldering.
- Finish the new concrete barrier at the County D overpass.
- Complete restoration along the outside driving lane and install guardrail in the driving lane.
- Complete final pavement markings in the driving lane and place temporary markings on the ramps.
- Remove paving ramps and will finish milling the mainline at WIS 23/82.
Traffic Impacts for the next 10 days:
- Current Closures
- The outside driving lane is closed between Fawn Court and County CX/Gail Lane and is expected to last until July 29.
- The southbound I-39 on and off ramps at WIS 23/82 interchange closed and expected to remain closed July 23.
- Upcoming Closures
- On July 27, crews plan to close the southbound I-39 on and off ramps at WIS 82/23 interchange and this closure is expected to last only one day.
- On July 28, crews plan to close southbound I-39 on ramp at County D and this closure is expected to last only one day.
- On July 29, crew plan to open the driving lane and close the passing lane of southbound I-39. This closure is expected to remain in place until Aug. 5.
- Tentatively scheduled for Aug. 3 is the full interchange closure for WIS 23 West/County P including closing WIS 23 between the ramps. This closure is expected to last 10 calendar days.