Schedule and Traffic Impacts
Page last updated: July 2, 2026
Schedule: April 22 to September 2026
Anticipated work scheduled for next week: Crews will:
- Begin paving asphalt in the inside passing lane and will start grading for guardrail replacement
- Replace the concrete approach at Fawn Court and will begin barrier wall repairs between County CX and County D
- Install erosion control for the north phase of the project
- Begin milling the inside passing lane
Traffic Impacts for the next 10 days:
- All lane closures and traffic control will be removed by noon July 2 for the holiday weekend.
- After the holiday, the outside driving lane on southbound I-39 is closed from County D to the Columbia County line.
- On July 6, crews will close the outside driving lane between Fawn Court and County CX/Gail Lane.
- On July 7, crews will close the inside passing lane between Fawn Court and County CX/Gail Lane. This closure is expected to last until July 14