Schedule and Traffic Impacts
Page last updated: Aug. 18, 2026
Schedule: April 9 to Oct. 31, 2026
Anticipated work scheduled: Crews will:
- Continue to work on pavement marking
- Install guardrail
- Repair concrete pavement
- Pave slope along WIS 52
- Install curb ramps along Bridge Street and WIS 52 Parkway
Traffic impacts (the next 10 days):
- Current Ramp Closed
- WIS 29 westbound to US 51 southbound (expected to open on Aug. 20)
- US 51 southbound to WIS 29 westbound (expected to open on Aug. 20)
- Future Ramp Closures
- County N northbound off-ramp (expected to begin on Aug. 20)
- County N northbound on-ramp (expected to begin on Aug. 20)
- Local street lane closures will be occurring along the following streets:
- County N (expected to begin Aug. 20)
- Sherman Street (currently closed)
- WIS 52 Parkway (currently closed)
- Bridge Street (currently closed)