Schedule
Construction begins: February 6, 2023
Anticipated completion: May 27, 2024
Traffic impacts/detours
April 4: I-39/90/94 southbound traffic will be diverted to the WIS 60 ramps for bridge girder placement.
- 10:30 p.m. – 4:30 a.m.
Stage 4 – February 22 – May 27, 2024
- All I-39 SB traffic is shifted over to the I-39 NB lanes and placed in a bi-directional configuration, with two 11-foot lanes in each direction separated with concrete barrier wall.
- WIS 60 maintains two-way traffic but may experience traffic slowdowns/rolling closures. WIS 60 will have nighttime closures for bridge demo.
Stage 5
- Lane closures along I-39 both NB and SB lanes, (no weekend closures).