Schedule
Construction starts: April 15, 2026
Anticipated completion: August 2026
Traffic impacts
I-39 will remain open to traffic with continuous single lane closures Monday through Thursday
I-39 will have double nighttime lane closures
County V interchange ramp closures will take place intermittently throughout the project, motorists are encouraged to utilize WIS 19 and WIS 60 during these closures
Weekly update
Current Construction Operations (Week of 8/30/2026):
- Nightly lane closures will occur on I 39 NB and SB between CTH V and the Dane County Line from Monday night to Friday morning. Work includes rumble strip installation and punch list items.
- All work to be suspended by Friday at noon for Labor Day Weekend.
- I39 off ramps to CTH V to be closed nightly starting at 8PM and reopening by 7AM.
- On ramp from CTH V to I39 to be closed nightly starting at 8PM and reopening by 7AM.
Upcoming Construction Operations (Week of 9/6/2026):
- Nightly lane closures will occur on I 39 NB and SB between CTH V and the Dane County Line from Tuesday night to Sunday morning as needed for punch list work.
- All work is suspended for the Labor Day Weekend from noon Friday to 6AM Tuesday morning.
- Ramps on I-39 to/from CTH V may be closed during this overnight period to facilitate this work. Detours will be provided with advance warning of ramp closures to guide motorists.