I-39 (County V to North Dane County line)

DeForest, Dane County

Schedule

Construction starts: April 15, 2026

Anticipated completion: August 2026

 

Traffic impacts

I-39 will remain open to traffic with continuous single lane closures Monday through Thursday

I-39 will have double nighttime lane closures

County V interchange ramp closures will take place intermittently throughout the project, motorists are encouraged to utilize WIS 19 and WIS 60 during these closures

 

Weekly update

Current Construction Operations (Week of 8/30/2026):

  • Nightly lane closures will occur on I 39 NB and SB between CTH V and the Dane County Line from Monday night to Friday morning. Work includes rumble strip installation and punch list items.
    • All work to be suspended by Friday at noon for Labor Day Weekend.
    • I39 off ramps to CTH V to be closed nightly starting at 8PM and reopening by 7AM.
    • On ramp from CTH V to I39 to be closed nightly starting at 8PM and reopening by 7AM.

Upcoming Construction Operations (Week of 9/6/2026):

  • Nightly lane closures will occur on I 39 NB and SB between CTH V and the Dane County Line from Tuesday night to Sunday morning as needed for punch list work.
    • All work is suspended for the Labor Day Weekend from noon Friday to 6AM Tuesday morning.
    • Ramps on I-39 to/from CTH V may be closed during this overnight period to facilitate this work. Detours will be provided with advance warning of ramp closures to guide motorists.