I-794 Bridge Structure Improvements

Milwaukee County

Project Details

This WisDOT project will make various improvements to the bridge structures along I-794 between the Marquette Interchange and the Lake Interchange in the city if Milwaukee.

Note: This project is not associated with the I-794 Lake Interchange study. To learn more about the I-794 Lake Interchange study, please visit the study page here: https://www.794lakeinterchange.wisconsindot.gov/

Project Improvements:

  • Deck sealing and polyester polymer concrete overlays of various bridges along I-794
  • High friction surface treatments
  • Concrete approach slab repairs
  • Concrete surface repair on parapet walls
  • New permanent pavement markings

This project will be completed over the course of two construction seasons:

  • 2026: Eastbound structures
  • 2027: Westbound structures

Traffic Impacts:

The majority of this project will be completed during the overnight hours with various lane, ramp, and full directional closures.

Access to local businesses and residences will be maintained.

Schedule:

This project is scheduled to begin in May 2026 and be completed by the end of 2027. Work will be paused during the winter months.

All work is weather dependent and subject to change.