Project Details
This project will make improvements to approximately 1.8 miles of WIS 60 (Main Street) from County P to Eagle Drive in the Village of Jackson, Washington County.
Improvements Include:
The entire project corridor will be resurfaced with HMA (Hot Mix Asphalt). In addition, the following improvements will be made:
- Updated traffic signals at County P, Industrial Drive, and Jackson Drive intersections with WIS 60.
- Reconstruct WIS 60 at Eagle Drive intersection to a modern roundabout
- Installation of retaining wall at the northwest corner of the roundabout
- Improve curb ramps to ADA standards
- New signage
- New pavement markings
Click here to view project improvement map
Traffic Impacts:
One-way traffic patterns in the eastbound direction on WIS 60. Westbound WIS 60 traffic will be detoured.
Access to local businesses and residents will be maintained.
Schedule:
Construction is anticipated to begin in April 2024 and be completed by late summer 2024.
Work is weather dependent and subject to change.