Project Details
This WisDOT project will stabilize the slope along the east side of WIS 57 in Ozaukee County, approximately 0.2 miles south of County K.
Improvements:
- Install vertical rigid elements (miniature pilings driven into the embankment to strengthen the slope)
- Culvert replacement
- Concrete pavement replacement
- Grading and storm sewer work
- Restoration and new pavement markings
- New pavement markings
Traffic Impacts:
This project will be completed in two stages:
- Stage 1: Northbound WIS 57 will be closed for culvert replacement
- This closure is anticipated to last approximately one week. Northbound WIS 57 detours will be posted during closure. The detour will utilize County D, County B, and County RR.
- Stage 2: WIS 57 will remain open to traffic in both directions with various lane and shoulder closures
Access to local businesses and residences will be maintained at all times.
Schedule:
Construction is scheduled to begin in late July and be completed by fall 2026.