Project Updates
June 27, 2024 Update:
Traffic:
- Remains in stage 2 (bi-directional traffic on westbound lanes)
- County W north leg is open to right turn in and out only
- Access for Black Bull Fireworks (south side of WIS 50) will be maintained across median at driveway entrance
This Week:
- Pavement removals, grading, select borrow, and base aggregate placement for eastbound WIS 50
- Pouring east expansion joint and parapet surface repairs on railroad bridge
Next Week:
- Finishing base aggregate placement on eastbound WIS 50
- Storm sewer, culvert, and underdrain installation at eastbound WIS 50
- Prep work for deck overlays at railroad bridge
- Holiday shutdown beginning end of workday 7/3; work to resume on 7/8
Future Work (2 weeks+):
- Deck overlays at railroad bridge week of 7/8
- Fine grading and trimming of base aggregate
- Eastbound mainline concrete pavement tentatively 7/11 or 7/12
March 20, 2024:
Construction to resume for 2024 season.
Click here: View 2024 project schedule