Project Overview
Construction began Tuesday, April 1, 2025, on 4.6 miles of WIS 42 between Manitowoc and Two Rivers in Manitowoc County. This includes construction on the West Twin River bridge and a full closure of WIS 42 between Manitowoc and Two Rivers.
TRAFFIC IMPACT: WIS 42 is closed and detoured to through traffic.
- If you have a destination in the work zone, such as Aurora Medical Center, you can use the closed portion of WIS 42.
- The roadway is open to business, properties and emergency services in the work zone.
- The roadway is closed to through traffic only… if you do not have a destination in the work zone, please use the detour route to help keep workers safe.
Read News Release: WIS 42 construction begins April 1
Project location
WIS 42 from Waldo Blvd in the city of Manitowoc to the West Twin River Bridge in the city of Two Rivers, Manitowoc County.
- View WIS 42 project limits on a map (PDF)
- View West Twin River bridge location (PDF)
- View project work zone and location in interactive map
Project purpose and need
The WIS 42 existing pavement is showing signs of deterioration. The existing beamguard has reached the end of its useful life and the metal culvert pipes under the highway are deteriorating. The bridge deck on the West Twin River bridge is nearing the end of its service life.
Project improvements
This is a resurface-level project with bridge deck and culvert work. Construction includes:
- Mill 2.5 inches of the existing surface and pave 2.5 inches of hot mix asphalt
- Concrete bridge deck overlay (West Twin River Bridge)
- Culvert replacement and cleaning
- Concrete base patching
- New curb ramps built to ADA standards
- Beamguard replacement
- Mirro Drive intersection realignment (closer to 90 degrees. Photo on right)
- Pavement marking
Construction benefits
Resurfacing will provide a smoother ride for motorists, extend the life of the pavement, and decrease future maintenance costs. Culvert repairs/replacements will help ensure proper drainage and lessen the likelihood of collapse. Mirro Drive realignment will provide a safer turning and crossing movement. Bridge overlay will extend the life of the bridge. Beamguard upgrades will provide a greater level of safety should impact occur.
WIS 42 will be CLOSED AND DETOURED to through traffic from April 1, 2025, through May 23, 2025, for bridge deck work and culvert replacements.
- Detour: Motorists will be directed to use US 10, County B, and WIS 310.
- Access to businesses and properties in the closed portion of the highway will always be maintained.
- Some closures will require approaching from the north or south on WIS 42 depending on location of culvert work.
During highway resurfacing operations following bridge and culvert work at the end of May, WIS 42 will remain open to traffic using lane closures and flagging operations to complete construction.
Schedule
Construction begins April 1, 2025, and is expected to finish in July 2025.
Temporary business signing
If business access is impacted by a closure or detour, temporary business signing may be placed by filling out a WisDOT business signing permit. All temporary business signing needs approval via the permit before placement to ensure it is in a safe location and does not pose a visual distraction or traffic hazard. The temporary business signing permit is free. Costs associated with creating the temporary sign are the responsibility of the business.
- Click the below link for instructions and a link to a fillable-form WORD application for the permit.
- Please email or mail the free permit to any of the contacts below.
Business Resource: WisDOT’s In This Together program
WisDOT recognizes businesses located in work zones or impacted by detour routes have special needs. WisDOT’s In This Together program is offered to businesses, organizations, and community leaders as an idea source as they plan for road construction in their area. It includes promotional examples, case studies, and a specially designed Business Coordination Guide with information on:
- Planning ahead
- Staying informed
- Keeping customers informed
- Tips for businesses
Project contacts
This project will have a dedicated construction project field office and construction project leader. For construction-related questions, please contact the construction project leader. For all other questions, please contact the WisDOT project manager.
Project construction project leader
Keith Process
E-mail: keith.process@meadhunt.com
Phone: (920) 619-3015
Construction Field Office
- 3612 Lincoln Avenue, Two Rivers, WI, 54241
WisDOT Project Manager, Manitowoc County
Brian Haen, P.E., Project Manager, Manitowoc County
Wisconsin Department of Transportation
944 Vanderperren Way
Green Bay, WI 54304
920-366-4788
brian.haen@dot.wi.gov