US 18 Resurfacing

Waukesha County

Project Updates

September 18 Update:

Completed Items:

  • Milling
  • Patching
  • Paving
  • Shoulder grading prior to paving
  • Markings from Oak Crest Drive and west
  • Cattle pass installation/restoration
  • Sidewalk and curb ramps
  • Loop detectors at Oak Crest Drive
  • Initial erosion control, traffic control, and staking
  • Guardrail removal
  • 4,000 ft. of new guardrail installed

Upcoming Work:

Upcoming work will be shouldering, topsoil placement, rip rap, and the electrical work for the signals at Oak Crest Drive.  Other work to be completed includes signals at Oak Crest Drive, rumble strips, pavement markings, signing, storm sewer and culvert work, and final restoration.