WIS 98, WIS 73 to Helm Street

Clark County

Project Overview

Construction consists of:

  • Replacing the existing concrete pavement in select areas of pavement failure due to poor soils
  • Replacing base material and adding geo-grid in those poor soils areas
  • Making concrete joint repairs
  • Completing culvert work, which includes:
    • Replacing, resetting, extending or cleaning culvert pipes
    • Attaching new apron end walls
    • Grading ditches from apron end wall to the road right of way
    • Placing rip rap at the end of culvert pipes and end walls
  • Replacing pavement markings