Project Overview
Construction includes:
- Removing 2 inches of the existing pavement in the rural segment and placing 3.25 inches of new asphalt pavement.
- Removing 3.25 inches of the existing pavement in the urban segment and placing 3.25 inches of new asphalt pavement.
- Installing centerline rumble strips.
- Cleaning or replacing culverts.
- Replacing guardrail and upgrading end terminals.
- Cleaning ditches.
- Replacing pavement markings.
- Upgrading sidewalk curb ramps in the village of Hixton.