Schedule
Bi-weekly update
Construction begins: April 8, 2024
- April 8th thru early June – Box culvert replacement work at Mud Creek (between York Center Road and Sun Prairie Road). This section of WIS 89 closed to thru traffic.
- End of April thru early June – Reconstruction of WIS 89 and County TV intersection. This section of WIS 89 and County TV closed to thru traffic.
- Early June to end of June – Mill and pave entire project limits under flagging operations (Avalon Road near Kestle Ridge golf course in Columbus to Clarkson Road just north of Waterloo)
Anticipated completion: Late June 2024
Traffic impacts
WIS 89 will be closed and detoured for work on the Mud Creek box culvert and for the reconstruction of the WIS 89/County TV intersection.
- Detour route: WIS 19 to WIS 73
- WIS 89 detour map
- Traffic control map
Additional lane closures will be handled with flagging operations.