Schedule and Traffic Impacts
Page last updated: June 28, 2024
Schedule: May 2 to August 2024
Anticipated work scheduled for next week: Crews will:
- Complete pavement removal from Necedah Road to Marathon Avenue
- Continue sewer work
- Pulverize and relay 800 feet south of WIS 173 to County line
- Grade pulverized material for asphalt paving
- Begin paving asphalt 800 feet south of WIS 173 to County line
Traffic Impacts for the next 10 days:
- Wood County: WIS 80 and WIS 173 will be closed to all traffic between Pine Street and Marathon Avenue in Babcock with no through access. Traffic is detoured via WIS 21, WIS 13, WIS 73 and WIS 173
- Wood County; WIS 80 will be closed to through traffic from the Juneau County Line to Pine Street in Babcock and from Marathon Avenue in Babcock to the WIS 80/173 intersection north of Babcock. Traffic is detoured via WIS 21, WIS 13, WIS 73 and WIS 173
- Wood County: WIS 173 will be closed to through traffic from the WIS 80/173 intersection south of Babcock to Pine Street in Babcock and from Marathon Avenue in Babcock to the WIS 80/173 intersection north of Babcock. Traffic is detoured via WIS 21, WIS 13, and WIS 73