WIS 73, Industrial Street to WIS 186

 Wood County

Schedule and Traffic Impacts

Page last updated: July 18, 2025

Schedule: June 23 to Sept. 30, 2025

Anticipated work scheduled: Crews will:

  • Install curb and gutter, concrete shoulder, topsoil, curb and gutter and sidewalk
  • Install erosion control at concrete surface drains

Traffic impacts (the next 10 days): WIS 73 traffic closures. (See map for details):

  • WIS 73 will be closed to through traffic until late September. Access will be maintained to local businesses and residents.