Schedule and Traffic Impacts
Page last updated: Sept. 20, 2024
Schedule: Aug. 5 to Oct. 14, 2024
Anticipated work scheduled for next week: Crews will:
- Finish milling the existing asphalt pavement from the Moccasin Creek bridge to WIS 54 and around the railroad crossing.
- Adjust the manhole covers after paving of the asphalt binder layer is complete.
- Work on joint and crack cleaning and perform any necessary patching in repair areas
- Place the mainline asphalt pavement, both the lower and upper layers through the end of next week.
Traffic Impacts for the next 10 days:
- Motorists will encounter single lane closures with flaggers.