Schedule and Traffic Impacts
Page last updated: May 30, 2025
Schedule: April 30 to July 2025
Anticipated work scheduled: Crews will
- Pour the deck overlays in the westbound lane.
- Finish installing the fence along the south side of the Jordan Pond structures.
- Apply the protective surface treatment to the decks and the pigmented surface sealer to the north parapets.
- Complete the removals, excavation and base aggregate placement on Torun Road under flagging operations.
- Pave the asphalt driveways at the parking lots at the intersection of WIS 66 and County J.
- Remove the temporary concrete barrier in the work zone as early as June 6.
Traffic impacts (the next 10 days):
- WIS 66 will be reduced to one lane with flaggers during daytime operations for work at the intersection of WIS 66 and Torun Road.
- The road is reduced to one 13-foot lane under the control of temporary signals for work on the structures over the Plover River at the Jordan Dam. This work will continue through early June.