Schedule and Traffic Impacts
Page last updated: Aug. 1, 2025
Schedule: April 30 to August 2025
Anticipated work scheduled: Crews will
- Complete the installation of the reflective epoxy pavement markings.
- Remove the pedestrian bypass at the Green Circle Trail Crossing that facilitated the pedestrian ramp construction.
- Pave the asphalt driveways that remain behind the concrete aprons and work on asphalt shoulder.
- Complete the topsoil work along finished driveways and follow with restoration landscaping items.
Traffic impacts (the next 10 days):
- WIS 66 will be reduced to one lane with flaggers during daytime paving operations from County Y to County J. This work will continue through early August.