Schedule and Traffic Impacts
Page last updated: Aug. 8, 2025
Schedule: April 30 to August 2025
Anticipated work scheduled: Crews will
- Complete the permanent pavement markings that remain.
- Complete the topsoil work along finished driveways and follow with restoration landscaping items.
- Complete the permanent signing installations.
- Remove the pedestrian bypass at the Green Circle Trail Crossing that facilitated the pedestrian ramp construction.
Traffic impacts (the next 10 days):
- WIS 66 will be reduced to one lane with flaggers during daytime paving operations from County Y to County J. This work will continue through early August.