WIS 66, Stevens Point Airport to County J

 Portage County

Schedule and Traffic Impacts

Page last updated: Aug. 8, 2025

Schedule: April 30 to August 2025

Anticipated work scheduled: Crews will

  • Complete the permanent pavement markings that remain.
  • Complete the topsoil work along finished driveways and follow with restoration landscaping items.
  • Complete the permanent signing installations.
  • Remove the pedestrian bypass at the Green Circle Trail Crossing that facilitated the pedestrian ramp construction.

Traffic impacts (the next 10 days):

  • WIS 66 will be reduced to one lane with flaggers during daytime paving operations from County Y to County J. This work will continue through early August.