Schedule and Traffic Impacts
Page last updated: May 2, 2025
Schedule: April 30 to July 2025
Anticipated work scheduled: Crews will
- Install the traffic control, temporary concrete barrier, and temporary signals to close the eastbound lane over the Plover River Structures.
- Complete the culvert crossing transition grading on WIS 66 west of WIS 66/County Y intersection.
- Patch the asphalt over the culvert work and culvert transition area.
- Install storm sewer at the County J and WIS 66 intersection.
- Begin the deck overlay preparation on the eastbound lanes of the structures located at Jordan Pond.
Traffic impacts (the next 10 days): WIS 66 will be reduced to one lane with flaggers as the culvert pipe crossing is installed during daytime operations.
The road will be reduced to one 13-foot lane under the control of temporary signals for work on the structures over the Plover River at the Jordan Dam. This work will begin as early as May 1 and will continue through the month of May.