Schedule and Traffic Impacts
Page last updated: June 28, 2024
Schedule: May 6 to Aug. 8, 2024
Anticipated work scheduled for next week: Crews will:
- Continue work on the deck of the bridge.
Traffic Impacts for the next 10 days: Traffic has been shifted to the west side of WIS 55, traveling on a temporary bypass lane around the work area. Traffic will be maintained by temporary traffic signals throughout this time frame.