Schedule
May 4, 2015 – Construction began
June 4, 2015 to early September 2015 – WIS 54 closed between Vineyard Drive and Short Drive, Maple Drive closed between Rosalie Parkway and Mecca Drive
September 2, 2015 – Crews opened the intersection
late-September or early-October – Crews will install permanent street lighting at the intersection