Schedule and Traffic Impacts
Page last updated: Sept. 17, 2025
Schedule: Sept. 8 to Oct. 24, 2025
Anticipated work scheduled: Crews will:
- Remove concrete curb and gutter
- Remove curb ramp on the northbound side of WIS 44 from the Grand River Bridge north to Precision Drive
- Pour concrete curb and gutter, and sidewalk at removal locations
Traffic impacts (the next 10 days):
- Work occurring within parking lanes or on sidewalks. Flagging operations as needed.
- Pedestrian detours and temporary crosswalks to move pedestrians around sidewalk work.