Schedule
Construction currently scheduled for 2015
- May-July – Center St. (Maple Ave.–Front St.) construction
- May–Sept. – Front St. (Center St.–Spring St.) construction
- July–Sept. – Spring St./Front St. intersection construction
- Aug.–Oct. – City of Beaver Dam Spring St. (Maple Ave.-Front St.) construction
Status/phase
Final design and coordination work is being completed in 2014, with construction currently scheduled for 2015.