WIS 32, Julia Creek and Scott Creek Culverts

 Three Lakes, Hiles

Schedule and Traffic Impacts

Page last updated: May 5, 2022

Schedule: May 2, 2022 to September 9, 2022

Julia Creek Update: 

  • April 29, 2022 Update: Due to the unavailability of materials for construction at Julia Creek, work is pending until materials can be delivered. The new tentative schedule for construction at Julia Creek will be after Labor Day weekend 2022 or Spring 2023 before Memorial Day weekend.

Overall Traffic impacts:

  • Scott Creek
    • Work at Scott Creek is currently anticipated to begin on Monday June 13, 2022 pending the same materials delivery issues as Julia Creek. If the delivery of materials is anticipated to occur, the installation of erosion control and traffic control devices will begin one week prior.
      • After June 15, a full closure will be allowed for a maximum of 15 calendar days.
        • Detour will be US 45 south to US 8 east to WIS 32 north.
      • Once the detour is removed, WIS 32 at this location will be open to a single lane with flagging or temporary stop signs.
  • Pine Creek
    • A full closure will be in place from July 5 until September 1.
      • Detour will be US 45 south to US 8 east to WIS 32 north.
    • Once the detour is removed, WIS 32 at this location will be open to a single lane with flagging.
  • During other small culvert work
    • WIS 32 will be open with a single lane closure and flagging operations.
Full closures on WIS 32 are shown here in orange for Julia Creek, Scott Creek, and Pine Creek.