Schedule and Traffic Impacts
Page last updated: July 2, 2026
Schedule: April 27 to July 24, 2026
Anticipated work scheduled: Crews will:
- Finish installing right of way fencing
- Pave the slope under County Y overpass
- Install signing
- Reconstruct various median inlets
- Restore miscellaneous areas
Traffic impacts (the next 10 days):
- WIS 29 has been shifted to bi-directional travel on the eastbound lanes between County Q and Bass Lake Road, with one lane open in each direction and speeds reduced to 55 mph.
- Westbound travel will be restricted to 14 feet.