WIS 29, Slope Stabilization

Shawano County

Schedule and Traffic Impacts

Page last updated: Sept. 26, 2025

Schedule: Aug. 11 to Oct. 30, 2025

Anticipated work scheduled for next week: Crews will:

  • Complete slope stabilization
  • Begin milling on WIS 29

Traffic Impacts for the next 10 days:

  • Traffic on WIS 29 has been shifted to all traffic in single lanes along eastbound WIS 29. The crossovers are located 1.0 miles west of the WIS 22 ramp. The crossovers end approximately 1.3 miles east of WIS 22 ramp. The maximum lane width will be 14 feet. Traffic will be in this layout until mid to late October.