Schedule and Traffic Impacts
Page last updated: July 18, 2025
Schedule: June 2 to Oct. 6, 2025
Anticipated work scheduled: Crews will:
- Finish milling the asphalt layer of the right lane in each direction for the entire project length.
- Pave the base layer of asphalt on the right lane in each direction.
- Begin paving the surface layer of asphalt on the outside shoulder, starting on the west end of the project in the eastbound direction.
Traffic impacts (the next 10 days):
- The right lane is closed to traffic in both the eastbound and westbound directions on WIS 29 from Purple Martin Lane to the Little Rib River.
- Daily ramp closures will occur to allow milling and paving operations on WIS 29 to pass through the exit and entrance portions of ramps.