Schedule and Traffic Impacts
Page last updated: July 11, 2025
Schedule: June 9 to Oct. 17, 2025
Anticipated work scheduled: Crews will:
- Work on WIS 29 eastbound and westbound approach slabs at WIS 13 overpass outside lanes
- Finish constructing and paving the temporary median crossover for WIS 29 westbound traffic on west end of project
- Pave WIS 29 westbound outside asphalt shoulder at WIS 13 overpass
- Install guardrail for WIS 29 westbound outside lane at WIS 13 overpass
- Start WIS 29 westbound concrete repairs and replacements
Traffic impacts (the next 10 days):
- WIS 29 eastbound lane closure from WIS 13 to County E South to Oct. 3
- WIS 29 westbound lane closure from County E South to WIS 13 to Oct. 3
- WIS 29 westbound off ramp closure to Spruce Street from July 15 to Oct. 3