Construction includes:
- Repairing the existing concrete pavement on WIS 29 and the ramps at the County E interchange and then overlaying the roadway and ramps with asphalt pavement
- Overlaying the ramps at Cardinal Avenue east of Owen and Hi Line Avenue in Abbotsford with asphalt
- Replacing guardrail to meet current WisDOT standards
- Repairing the decks on the east- and westbound WIS 29 bridges over County D and the railroad tracks to the east and placing a thin bonded polymer overlay over them
- Cleaning and repairing culverts to improve drainage
- Repairing the median inlets near Owen adjacent to concrete barrier wall
- Completing minor grading of ditches