WIS 29, County D to WIS 13

Clark County

Project Overview

Construction includes:

  • Repairing the existing concrete pavement on WIS 29 and the ramps at the County E interchange and then overlaying the roadway and ramps with asphalt pavement
  • Overlaying the ramps at Cardinal Avenue east of Owen and Hi Line Avenue in Abbotsford with asphalt
  • Replacing guardrail to meet current WisDOT standards
  • Repairing the decks on the east- and westbound WIS 29 bridges over County D and the railroad tracks to the east and placing a thin bonded polymer overlay over them
  • Cleaning and repairing culverts to improve drainage
  • Repairing the median inlets near Owen adjacent to concrete barrier wall
  • Completing minor grading of ditches