WIS 29, Bridge Overlays

 Marathon County

Schedule and Traffic Impacts

Page last updated: Sept. 5, 2025

Schedule: Sept. 2 to Oct. 24, 2025

Anticipated work scheduled: Crews will:

  • Remove the asbestos abatement that is necessary on WIS 107.
  • Begin excavation and removals at WIS 107.
  • Remove the old polymer overlay in the outside lanes of the WIS 107 bridge deck.
  • Work on the approach slab and deck repairs in the outside lane at WIS 107.

Traffic impacts (the next 10 days): 

  • The outside lane on WIS 107 over WIS 29 will be closed to traffic in both the northbound and southbound directions. The inside lane in both directions will be open to traffic with an 11 foot width restriction.