Schedule
Current (this year)
- 2014 – Construction
Future (next year and beyond)
- Fall 2015 – Construction scheduled to be completed
Past (anything prior to today)
2013
- Fall 2013 – Milton Bypass north to County N open to traffic
2012
- Construction started
2011 and older
- Fall of 2011 – Real estate acquisition completed
- 2009 – Real estate acquisition started
The studies for this project have been completed and the project segments are in various stages of construction:
- Segment 3 (Milton to Fort Atkinson) – Scheduled for construction 2012-2014
- Segment 8 (Watertown to WIS 60 East) – Scheduled for construction 2013-2015
- Segment 1 (Janesville to Milton) – Completed in 2012
- Segment 2 (WIS 59 relocation at Milton) – Completed in 2009
- Segment 4 (Fort Atkinson bypass) – Completed in 2011
- Segment 5 (Jefferson bypass) – Completed in 2011
- Segment 6 (Jefferson to Johnson Creek) – Completed in 2011
- Segment 7 (Johnson Creek to Watertown) – Completed in 2012