WIS 26 Corridor Expansion

Segment 8 - Janesville to Watertown - Dodge, Jefferson and Rock counties

Schedule

Current (this year)

  • 2014 – Construction

Future (next year and beyond)

  • Fall 2015 – Construction scheduled to be completed

Past (anything prior to today)

2013

  • Fall 2013 – Milton Bypass north to County N open to traffic

2012

  • Construction started

2011 and older

  • Fall of 2011 – Real estate acquisition completed
  • 2009 – Real estate acquisition started

The studies for this project have been completed and the project segments are in various stages of construction:

  • Segment 3 (Milton to Fort Atkinson) – Scheduled for construction 2012-2014
  • Segment 8 (Watertown to WIS 60 East) – Scheduled for construction 2013-2015
  • Segment 1 (Janesville to Milton) – Completed in 2012
  • Segment 2 (WIS 59 relocation at Milton) – Completed in 2009
  • Segment 4 (Fort Atkinson bypass) – Completed in 2011
  • Segment 5 (Jefferson bypass) – Completed in 2011
  • Segment 6 (Jefferson to Johnson Creek) – Completed in 2011
  • Segment 7 (Johnson Creek to Watertown) – Completed in 2012