Schedule
Preconstruction meeting: April 18, 2024
- 5:30 – 6:30 p.m.
Burnett Town Hall
W6228 W Main St, Burnett
Construction begins: April 22, 2024
Anticipated completion: early August 2024
Traffic impacts
During resurfacing work:
- WIS 26 will remain open under single lane closures and flagging operations.
During culvert pipe replacement:
- WIS 26 will be closed to through traffic and detoured utilizing WIS 33 and US 151.