WIS 26 (WIS 33 to South of Milligan Road)

Burnett to Chester, Dodge County

Schedule

Preconstruction meeting: April 18, 2024

  • 5:30 – 6:30 p.m.
    Burnett Town Hall
    W6228 W Main St, Burnett

Construction begins: April 22, 2024

Anticipated completion: early August 2024

 

Traffic impacts

During resurfacing work:

  • WIS 26 will remain open under single lane closures and flagging operations.

During culvert pipe replacement:

  • WIS 26 will be closed to through traffic and detoured utilizing WIS 33 and US 151.