Project Overview
Construction includes:
- Removing a portion of the existing pavement from the bridge over I-94 to the railroad bridge and placing new asphalt pavement
- Recycling a portion of the existing pavement, mixing it with a stabilizing agent, relaying it and placing new asphalt over the roadway from the railroad bridge to County D
- Adjusting or replacing guardrail
- Completing culvert maintenance
- Upgrading pedestrian curb ramps and traffic signals
- Replacing pavement markings
Building roundabouts on WIS 25 at the north and south junctions of County BB will be constructed through a separate future project.