Construction includes:

  • Removing a portion of the existing pavement from the bridge over I-94 to the railroad bridge and placing new asphalt pavement
  • Recycling a portion of the existing pavement, mixing it with a stabilizing agent, relaying it and placing new asphalt over the roadway from the railroad bridge to County D
  • Adjusting or replacing guardrail
  • Completing culvert maintenance
  • Upgrading pedestrian curb ramps and traffic signals
  • Replacing pavement markings

Building roundabouts on WIS 25 at the north and south junctions of County BB will be constructed through a separate future project.